Annual operating cost does not settle the location decision if one site can start later. Suppose site A with backup faces an additional three-month connection delay relative to site B. Lost production contribution during that interval is assumed to be 150,000 per month, giving a one-time delay cost of 450,000. The figure represents a stated opportunity-cost assumption, not a forecast of revenue, and excludes costs already counted elsewhere.
Adding that delay cost to a full-year steady-state comparison raises site A's illustrative first-year-equivalent burden to 1,270,500, compared with 900,000 at site B. This combination is a simplified appraisal device, not a calendar-year income statement: the operating costs describe a full operating year, while the delay is a separate initial penalty. A detailed project model would put expenditure and output on actual dates and include the operating costs avoided during the delay.
The annual saving of 79,500 would recover a 450,000 initial penalty after about 5.66 years on an undiscounted basis. With ten year-end annual savings and an 8 percent discount rate, the present value factor is the sum of 1 divided by 1.08 raised to each year from one through ten, or 6.71008. Savings have a present value of approximately 533,451; subtracting the initial penalty leaves approximately 83,451.
That narrow positive result is sensitive to the horizon, discount rate, and persistence of the operating advantage. It also omits differences in taxes, labor, logistics, emissions compliance, land, and terminal values. The exercise therefore cannot select an actual location. It demonstrates that a connection delay can dominate short-term savings and that the importance of a tariff advantage depends on how long the project operates after the delay.
The contractual status of a connection should consequently be examined directly. An application, a preliminary offer, an accepted agreement, construction progress, energization, and firm operating capacity are different stages. A location announcement based on an unconfirmed capacity date exposes the project to a different risk from a site with an energized connection. The expected date should be tied to the network works and approvals required, rather than to a promotional timetable.
Germany's network-expansion monitoring illustrates this stage distinction at a system level. It records planning and construction progress for specified transmission projects and explicitly excludes distribution-line projects. Those records can help establish wider network development, but they do not verify the date or capacity of a particular industrial distribution connection. Bundesnetzagentur, network expansion monitoring, second quarter 2026.